How to Calculate Wastewater Treatment Volume in Electroplating Production Lines

31 Jul.,2025

How to Calculate Wastewater Treatment Volume in Electroplating Production Lines

 

Author: Marisa

The calculation of wastewater treatment volume for electroplating production lines typically considers:

  1. Water Consumption Method
    Treatment Volume ≈ Total Water Intake × Recycling Ratio
    (Recycling ratio usually 60%-90%, depends on water reuse system efficiency)

  2. Tank Volume Method
    Daily Volume(m³) = ∑(Tank Volume × Water Change Frequency × Number of Tanks)

  3. Empirical Formula
    Small/Medium Lines: 0.2-0.5 m³/m² (plated surface area)
    Automated Lines: 0.1-0.3 m³/m²

  4. Peak Flow Consideration
    Apply simultaneous discharge factor (typically 0.6-0.8)

Typical Value: Conventional lines ~5-15 m³/day·standard production line

Note: Actual calculation should consider specific process parameters and local environmental regulations.